2. There are two methods of connecting system controls to the boiler using either 230v or low voltage controls.
For 230v controls connect to the green plug supplied in the fittings pack.

 

3. The green plug is then connected on to the PCB inside the control box. If low voltage controls are used connect these to the terminal block on the back of the control box. The blue link wire must be removed.